Upon completion and testing
of the construction
of a sanitary sewer improvement, a District
representative will issue a Letter of Completion & Compliance,
signifying to the owner/developer to begin the dedication process.
All dedication documents shall be submitted within 60 days of
receiving the Letter of Completion & Compliance. Documents that need
Board action are required to be submitted on or prior to the last
Wednesday each month. |
|
|
Dedication Ordinance |
 |
All final testing reports (Ex. Manhole
Vacuum, Mandrel, and Low Pressure Air Testing Results) must be sent
by the developer to the Indiana Department of Environmental Management (IDEM)
http://www.in.gov/idem/
Your transmittal shall include your IDEM
permit number and name of the construction project as noted on the
permit. CTRWD will require receipt of transmittal to verify that the
specified documents were sent and received by IDEM. This receipt
will be part of the required documentation for dedication.
Indiana Department of Environmental Management
Office of Water Management
100 North Senate Avenue
P.O. Box 6015
Indianapolis, IN 46206-6015
Fax: (317)232-8637
|
 |
Submit as-builts to
the inspecting engineer for acceptance. |
| |
 |
1 Final Set of As-Builts - Paper |
The owner/developer shall submit final
as-built drawings to the District prepared by a licensed surveyor or
engineer. The set shall include one paper, one mylar and one digital
submission per
Hamilton
County's Digital Submission Standards. |
 |
1 Final Set of As-Builts - Mylar |
 |
1 Final Set of As-Builts - Digital |
| |
|
 |
Engineer's
Certificate |
States the
improvements to be dedicated have been constructed in strict
conformity with the approved plans and specifications and have
passed all required tests. |
|
|
|
| |
|
|
 |
Final Recorded Plat |
The owner/developer
shall provide final recorded plats or surveys with the recorded
instrument numbers clearly visible as well as all road
right-of-ways, utility easements, and boundary lines. All sewer
improvements shall be certified to be within the easements depicted. |
 |
Exclusive
Sanitary Sewer Easement |
 |
Non-Exclusive
General Easement |
| |
|
|
 |
Bill of Sale |
The
owner/developer shall convey the sewers and facilities to the
District utilizing a Bill of Sale. If the improvement are located
outside a public right-of-way or platted easement, use the Grant of
Easement & Bill of Sale |
 |
Grant of
Easement & Bill of Sale |
|
|
|
| |
|
|
 |
General Warranty Deed |
If a lift
station or similar facility is constructed and conveyed to the
District, a General Warranty Deed shall be required. |
|
|
|
|
|
|
 |
Maintenance Agreement |
The owner/developer shall supply a Maintenance Agreement
prior to Board
approval/dedication of the sewers. |
|
|
|
|
|
|
 |
Three Year Maintenance Bond |
The owner/developer will file with the
District a Maintenance Bond covering a three year period and
for 10% of the documented construction costs with in 60 days of the
Board's approval. |
|
|
|
| |
|
|
| |
|
|
| |
|
|